I was in Mexico City with Paco Vega to install a new Evotherm injection system for PINFRA last week. They are one of the largest asphalt contractors in Mexico and have a new contract with Mexico City government. Here is Paco Vega, MWV’s account manager in Mexico, inspecting the mix that was made at 240 - 250 F. We installed the equipment and got mix out to the job all in one (long) day ... another testament to how easy it is to use Evotherm Warm Mix Technology. That night, PINFRA continued on their own with 400T of mix sent out to a resurfacing job elsewhere in the city.
Author: Michael Plouff















Comments